Brantgate Solar Farm Project





Approval: November 12, 2013
START: October 1, 2013
END: October 25, 2013

Located in part of Lots 1 and 2 on Concession 11 in Brant County, the project site is located on approximately 32 hectares. The solar farm will be designed to produce 8 megawatts (AC) of power under the Feed-In Tariff (FIT) program that is currently offered by the Ontario Power Authority. The farm will use crystalline photovoltaic (PV) modules. The project will consist of approximately 44,000 PV modules, which will be grouped in arrays tilted and facing south. The module arrays are designed to be roughly 4.0 meters in height and they will be surrounded by a perimeter fence. Indigenous grasses/groundcover could be allowed to grow beneath and between the solar arrays.

 

Project Benefits:

  • Potential economic benefit of a one-time payment of $125,000 based on Net Present Value of $12,000 per year royalties ($1,500 per MV) for 20 years.
  • Employment opportunities potentially available through the contractor.

Haldimand Tract Map

Agreements