Project Description
PORT DOVER AND NANTICOKE WIND PROJECT
Port Dover and Nanticoke Wind is a 105 MW wind project located on 28, 000 acres in Haldimand and Norfolf Counties.
Project Information: At Time of Engagement
Capital Power’s, Port Dover and Nanticoke Wind Project is generating 105 megawatts in renewable energy which is being sold to the Ontario Power Authority under the Feed in Tariff (FIT) program. The project is owned and operated by Capital Power, and is located in the Counties of Haldimand and Norfolk, Ontario. This project commenced operation in November 2013 and consists of 58 turbines.
Project Status
These benefits align with the principles of perpetual care and maintenance.
This project commenced operation in November 2013
Six Nations is directly or indirectly involved with 560MW of renewable energy
Community Benefits
Royalty Payment of $3,350/MW/year ($349,740), estimated at $6.99 M over 20 years
Education Scholarship:
• Annual scholarship payment of $15,000 to Grand River Post Secondary Education ($300,000 over 20 years).
Project Update
Please note: This section includes the most recent/updated information regarding the project. Based on community engagement feedback at the time of engagement, project updates may differ.
Port Dover and Nanticoke Wind reached commercial operation in November 2013. Six Nations of the Grand River Development Corporation receives an annual community benefits payment of $3,350/MW/year ($349,740)
START DATE
April 21, 2014
END DATE
May 23, 2014
PROJECT STATUS
ENGAGEMENT PARTNERS
WEBSITE
DOCUMENTATION
News + Media
- Port Dover and Nanticoke Wind- Press Release April 16, 2014
- Port Dover and Nanticoke Wind-Haldimand Tract Map